Date 01/02/2022.
Work on turbo ventilator:
Procedure:
- Measure the diameter of chimney.
- chimney pipe diameter=166mm
- Measure the diameter of flange.
- flange pipe diameter=208mm
- Rivet diameter.
- Rivet diameter=7mm
- center of rivet to center of chimney.
- center of rivet to chimney pipe center=12mm
- then we make base mount for turbo ventilator
- For base mount we take a MS sheet and cut on plasma machine

7. after that we take a sheet and some part molud in moulding machine and some part mould manually.

8. After that we work on moulding and drilling operations in M.S sheet
Date 03/02/2022

we are doing same drilling and riveting as on 01/02/22.
operation in one side M.s sheet base mount.
Date (04/02/2022)
we riveting on another side of MS sheet base mount
Date (05/02/2022)

9. The curve plate is placed inside the base mount.
Date (08/02/2022)

10.we paint the base mount with help of compressor, red oxide ,painting color.
Date (12/02/2022)

11. We finally installed the turbo ventilator on top of the kitchen.
1)Problem Identified :
leaking of water through base of ventilator.
for that we make tar and use for prevention of leaking water.
Result:
After fitting the turbo ventilator, we noticed that the smoke from the kitchen was decreasing and coming out of the chimney.